New analysis reveals the full scale of sluggish housebuilding across the borough, reports James Cracknell

More than 5,600 homes that have planning permission remain unbuilt across Enfield borough – enough to meet the borough’s annual housing target four times over.
Delays with Enfield Council’s flagship housing development, Meridian Water in Edmonton, have been well documented – where 3,025 new homes with planning permission still await construction. Several other major housing schemes also remain unbuilt, however, with work yet to start on a further 2,486 homes.
When small sites with permission are also added to the equation, it means there are 5,661 homes in total awaiting construction across Enfield.
This figure doesn’t include various estate redevelopments being led by the council – such as Joyce and Snells – where work is underway, nor schemes that were only approved in the past year. Also omitted are schemes where permission has lapsed – such as Colosseum Retail Park.
The borough’s annual housebuilding target, as set by the London Plan, is 1,246. However, this number has consistently been missed since the plan was agreed. According to the government’s ‘housing delivery test’, just 77% of Enfield’s target was reached across the three years up to 2025.
But the council’s failure to meet its London Plan target comes amid long delays to several major schemes across the borough.
Construction yet to start
The single biggest privately-led development site with permission is Edmonton Green Shopping Centre. Crosstree Real Estate Partners, which bought the site for £72million in 2018, won permission in 2022 for 1,438 new homes.
The development is designed to regenerate the town centre and would see the existing 1960s-era shopping mall knocked down and replaced. The last significant update on the scheme’s progress came in March 2024, when Crosstree confirmed it would be adding second staircases to the tall buildings included in its plans.
Crosstree has not responded to a request for comment from the Dispatch.
Further south along Fore Street, a 100% affordable housing scheme in Angel Edmonton was approved by councillors at the fourth time of asking in 2023.
Developer Social Capital Partners won permission to demolish The Gilpin’s Bell Pub and build 110 social-rent homes plus commercial space that could be used to provide a replacement public house. But there’s still no sign of any construction work starting, and the pub continues to trade.

Plans by the same developer for another 100% affordable development in Enfield Highway won permission in 2024. It is set to provide 100 homes for social rent in Moorfield Road. But two years later, construction hasn’t begun.
Invited to comment, Shane O’Neill, principal of Social Capital Partners, said: “We remain wholly committed to bringing these developments forward and firmly believe they represent an important opportunity for Enfield to address its housing challenges.
“With the continued support of the Greater London Authority, we remain confident in the merits of both schemes and look forward to working constructively with all stakeholders to translate this shared ambition into much-needed homes.
“Our commitment to these developments has not diminished, and we remain ready to progress them as soon as the necessary arrangements are in place.”
Another Enfield Highway site, where The Black Horse Pub once stood in Hertford Road, won permission in 2024 for 38 new flats. But the site remains vacant, as it has done for nearly a decade. According to Companies House, developer White Gold Properties entered administration in August.
At another former pub site, The Cart Overthrown in Edmonton, plans for 61 homes were first approved on appeal in 2022, before bring amended in 2025 to reduce their scale. Developer Ercan Ucur could not be reached for comment.
A modular housing scheme in Bullsmoor also remains unbuilt, despite obtaining permission in 2023. Developer Zed Pods had planned 29 “factory built” homes in Bullsmoor Lane, at the junction with the A10. The company did not respond to a request for comment.
A revised scheme by Places for London – Transport for London’s development arm – to build 373 homes on the car parks at Cockfosters Station was given the go-ahead in February, four years after the original plans for 351 homes were approved.
The same developer admitted earlier this year that another stalled housing scheme next to Arnos Grove Station was still a long way from construction. Plans for 162 homes were approved on appeal in 2022, and later amended in 2024, but a spokesperson said “changing market conditions” meant there was still no construction timeline.
Regarding the Cockfosters scheme, a spokesperson said: “Currently the site for our Cockfosters development is being used by colleagues at Transport for London as part of the programme to deliver the new Piccadilly Line trains, however, we are looking forward to starting on site in late 2027 and hope to complete the delivery of these vital homes in 2031.”

Last year the council agreed to purchase a site in Clay Hill where 58 affordable homes are planned to be built. The proposed redevelopment of Anglo Aquatic, a now-closed plants supplier in Strayfield Road, won approval three years ago. Another council-owned site is due to see up to 120 new homes added to Exeter Road Estate. Permission was won back in 2022, and revised in 2025, but work has yet to begin.
Invited to comment on these two council-led sites as well as the overall situation with stalled housing development across the borough, cabinet member for housing Lee Chamberlain said: “Since taking office in May, Enfield’s administration has pursued an ambitious programme to deliver the homes our growing borough needs.
“This ambition is outlined in our recently published Council Plan, Economic Growth Plan and Housing and Growth Strategy. The council is both building new council homes directly and working with developers, housing providers and investors to unlock housing across a range of sites and tenures.
“We recognise the significant economic challenges facing housebuilding, but our commitment remains clear – to deliver more, good-quality homes that local people can afford, with a particular focus on affordable, family-sized and specialist housing.”
Regarding small sites, of 20 homes or fewer, the council last month agreed a new strategy which aims to “support schemes that have the potential to make an immediate contribution to housing supply, recognising that securing deliver on consented sites can often bring forward new homes more quickly than progressing entirely new planning applications”.
Developments ditched
Meanwhile, in the past couple of years, four major housing schemes in the borough have been ditched entirely.
At Colosseum Retail Park in Southbury, Neat Developments had won approval for 1,800 homes in 2020, but the planning permission expired in 2024. The same developer has since submitted plans for 1,150 homes at Southbury Leisure Park, on the opposite side of the A10, where Cineworld Cinema would be demolished.
In Brimsdown, developer Stonegate Homes won permission in 2021 for a 148-home scheme in Green Street, before plans were amended in 2023, and finally ditched in 2025.
At Southgate Office Village, plans by Viewpoint Estates to build 216 homes were granted permission on appeal in 2021, but were cancelled last year in favour of an alternative proposal to convert existing offices into flats.
And in New Southgate, City and Suburban Homes won permission to build 182 homes on a former gasholder site in Station Road near the North Circular, but it was confirmed in 2025 the plans had been axed.
A complex problem
Matt Burn, from local campaign group Better Homes Enfield, admits the situation is complicated but that, with nearly 6,000 homes remaining unbuilt across the borough, it’s clear the system is broken.
He said: “This analysis shows that we’re relying too heavily on private developers to deliver the homes Enfield needs. That approach simply isn’t working. Developers have to make a profit, and the homes that make them money aren’t necessarily the homes that local people need or can afford.
“The situation is complex, but ultimately we have a broken housebuilding model that relies on ever-rising house prices. Developers have often paid too much for land, and with construction and borrowing costs rising, many now find they can’t afford to build, even when they’re providing little or no affordable housing.
“Substantial public investment in genuinely affordable housing is now not just essential, but also a wise use of public funds. Otherwise, we’ll keep approving thousands of homes that never get built, while the housing crisis deepens. The government’s recent increase in funding for social and affordable housing is welcome, but much more is needed.”
Local news needs your support
We are proud that we were at the forefront of reporting on the recent local elections. We can’t do this without the support of our readers.
Independent news outlets like ours – reporting for the community without rich backers – are under threat of closure, turning British towns into news deserts.
If our coverage has helped you understand our community a little bit better, please consider supporting us with a monthly, yearly or one-off donation.
ACT NOW!
Monthly direct debit
Annual direct debit
£5 per month supporters get a digital copy of each month’s paper before anyone else, £10 per month supporters get a digital copy of each month’s paper before anyone else and a print copy posted to them each month. £50 annual supporters get a digital copy of each month's paper before anyone else.
More information on supporting us monthly or yearly
More Information about donations